Current Works

Extended hours for truck movements to reduce peak hour demand

Truck movements to import material for earthworks at the SIMTA site will take place during extended hours from the end of this month, to reduce our vehicles’ use of the M5 and Moorebank Avenue during the morning and afternoon peaks. From March 30, vehicles will be approved to arrive, deposit their loads and then leave…

Nighttime sewer main installation

SIMTA contractor Fulton Hogan will be installing a sewer main adjacent to Moorebank Avenue during nighttime hours from 26 March. Work will take place in three locations near the Piccolo Me Café, the entry to Moorebank Logistics Park and within our site near the Target Warehouse. Work is scheduled outside of standard construction hours from…

Asbestos removal, Moorebank Precinct West

SIMTA contractor BMD will be removing bonded asbestos contaminated material from Moorebank Precinct West during the week commencing 30 March. Work will be undertaken in accordance with Work Safe requirements (under licence) and include air monitoring to ensure no asbestos particles leave the work area. As part of the control measures, the work crew are…

Service installation under Moorebank Avenue

SIMTA contractor BMD Constructions will be locating sewer services under Moorebank Avenue as part of the Moorebank Intermodal Terminal development. The work will be carried out as night-works between Monday 2 March and Friday 13 March, from 8am to 5am daily. Activities include survey location, pot holing and excavating. This work has been scheduled outside…

Nighttime asphalt work within SIMTA site

SIMTA contractor Fulton Hogan will be asphalting sections of the interior road of Moorebank Intermodal Terminal near the Target Warehouse. Work is scheduled at night on Wednesday 18 and Thursday 19 December 2019. This work has been scheduled outside of regular construction hours to avoid disruption to the business trading at this location and its…

Tree clearing west of Moorebank Avenue

BMD Constructions is commencing work for the Moorebank Avenue Upgrade as part of the Moorebank Intermodal Terminal. As part of that, trees to the west of Moorebank Avenue will be removed in coming weeks. Work will take place adjacent to Moorebank Avenue between Bapaume Road and 100m south of Chatham Avenue. Work will be completed…

Concrete pours for new warehouses

SIMTA contractor Hansen Yuncken is completing concrete pours within the Moorebank Precinct East construction site during November and December. Some of this work is required outside of regular construction hours due to the size of the concrete pours being completed. These concrete pours may create additional noise during the early morning between 8 November and…

Work to impact Moorebank Avenue from August to October

SIMTA contractors Fulton Hogan and CPB will be conducting work along Moorebank Avenue from August to October, including some nightworks within our site and affecting adjacent roads, that will cause occasional interruptions outside of peak periods. Work will include the installation of upgraded utilities near Anzac Road and Piccolo Me, construction of internal roads and…

Water main work at Moorebank Avenue and Bapaume Rd

SIMTA contractor Fulton Hogan will connect a new water main at the corner of Moorebank Avenue and Bapaume Road on a date between Sunday 14 July and the night of Friday 19 July, in consultation with Sydney Water. Work to allow use of newly-installed water infrastructure is intended to occur between the hours of 7am…

Trenching night work near Piccolo Me café on Moorebank Avenue

SIMTA contractor Fulton Hogan will trench and backfill a driveway near Piccolo Me café at 400 Moorebank Avenue on the night of Tuesday 2 July. In the event of rain these works may need to occur the following night. Works to allow installation of a communications service will be undertaken between the hours of 4pm…