Current Works

Asphalting night work off Moorebank Avenue

SIMTA contractor Fulton Hogan will be carrying out pavement work for up to four nights from Tuesday 25  June – Friday 28 June inside the Moorebank Intermodal Terminal Development. Night work is planned to occur between the hours of 6pm and 5am, weather permitting. Partial lane closures will be required at the entrance of the…

Out of hours works on the ARTC Rail Corridor and SIMTA Rail Link

SIMTA contractor CPB will be undertaking track works to the SIMTA Rail Link from the ARTC rail corridor east of Georges River in June. Out of hours work will be required from 6pm Tuesday 11 – midnight Friday 14 June. These works are required to be undertaken during this period to ensure minimal disruption to…

Out of hours work off Moorebank Avenue

SIMTA contractor Fulton Hogan will be carrying out concreting and pavement works at night until November 2019. These works will carried out inside the SIMTA site. Night work is planned to occur from June until November between the hours of 5 – 7am and 6 – 8pm, on Monday to Friday. Works will also be…

Oversize deliveries and out of hours work, 1 – 2 June

SIMTA contractor CPB will be receiving oversize deliveries and undertaking correlating works outside of regular construction hours Saturday 1 June – Sunday 2 June. The deliveries of oversized plant equipment for a crane and traverser are required to be undertaken out of hours to minimise traffic disruption. Heavy vehicles will be using Moorebank Ave to…

Construction activity on Moorebank Avenue bridge

SIMTA contractor CPB will be carrying out work on the Moorebank Avenue bridge on Monday 13 and Tuesday 14 May. Work will be carried out between 9am and 3pm to avoid impacts on the road during the morning and afternoon peak. A contra-flow will be in place during the work. Please follow the direction of…

Night work adjacent to Moorebank Avenue

SIMTA contractor Fulton Hogan will be carrying out asphalt work at night next week at the entry to the Moorebank Logistics Park. Night work is planned to occur on Monday 13 and Tuesday 14 May between the hours of 8pm and 5am, weather permitting. Work involves the use of hand tools, tippers, paving machine, lighting…

Weekend rail construction, May 11 and 12

CPB Contractors will have crews working on the Southern Sydney Freight Line on the weekend of May 11 and 12, which may be audible to some residents in Casula and Glenfield. Work is taking place from late Friday night until early Monday morning to finalise signalling and other necessary infrastructure ahead of the SIMTA rail…

Weekend closure to resurface Moorebank Avenue rail bridge

To complete the road surfacing of the final alignment of Moorebank Avenue above the new rail underpass, a weekend closure of Moorebank Avenue either side of the Holsworthy-Glenfield rail line crossing will be required. The road will be closed to through traffic between Cambridge Avenue and Anzac Road from 9pm on Friday May 3 to…

Further helicopter movements for solar panel installation

SIMTA contractor Hansen Yuncken and its sub-contractors will continue their work using a helicopter to install solar panels to the roof of the warehouse under construction at the northern end of Moorebank Precinct East in coming weekends. The work, being carried out outside of standard construction hours for safety reasons, is scheduled for weekends during…

Daytime and night works on Moorebank Avenue throughout April

SIMTA contractors will be carrying out utility investigation and installation work adjacent to Moorebank Avenue throughout April. Work will be carried out during regular construction hours and as night works when required to minimise impacts to motorists during the morning and afternoon peak periods. Work will take place between the Holsworthy-Glenfield rail line and the…