Open For Consultation

Power supply upgrade – Junction Road and Anzac Road This consultation has now closed.

Plans for an electrical upgrade related to the Moorebank Logistics Park development are available to view until Wednesday 6 July 2022. Click here to download the report: Review of Environmental Factors – June 2022

Community members and interested stakeholders are invited to make formal submissions as part of the project’s Review of Environmental Factors.

The project includes installation of a new 33kV electricity supply from the eastern end of Junction Road to Heathcote Road at the intersection with Seton Road, and on Anzac Road from the intersection with Greenhills Avenue to the Moorebank Logistics Park site on Moorebank Avenue.

Pending approvals, construction is expected to commence by the end of 2022 and will take one year to complete, weather permitting.

Endeavour Energy is the Determining Authority for the proposed development, and so approval under Part 5 of the Environmental Planning and Assessment Act 1979 is required. As part of the construction and installation works, road opening approvals would be required from Liverpool City Council, in accordance with the Roads Act 1993.

Have your say

To review and comment on the plans, or seek additional information, please use the contact details below:

Phone: 1800 986 465 (24/7)

Email: [email protected]

Write: Level 15, 207 Kent Street, Sydney NSW 2000